Followers of our Twitter feed have been enjoying some behind the scenes photos from the expansion works at our Centro facility. We’ve put together a quick post here with some highlights:
- Bases ready for installation of additional 5 air conditioning units
- Installation of new ultra-secure dedicated caged area
- Additional 250kW Carrier chiller arrives on-site
- Delivery of new 2,500L chiller water buffer tank
- Delivery of UPS batteries to support 400kW at 2N redundancy
- UPS battery build nearing completion