Centro phase 2 fit-out update

Followers of our Twitter feed have been enjoying some behind the scenes photos from the expansion works at our Centro facility. We’ve put together a quick post here with some highlights:

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – Final commissioning works

HV feed from EDF fully tested and energised

HV feed from EDF fully tested and energised

UPS batteries ready for installation and testing

UPS batteries ready for installation and testing

Final UPS connections and testing

Final UPS connections and testing

Access control system installed and tested

Access control system installed and tested

Splicing and testing fibre connections for our DWDM ring

Splicing and testing fibre connections for our DWDM ring

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – Raised access floor and suspended ceilings

First 1,000 floor tiles arrive on-site

First 1,000 floor tiles arrive on-site

Floor tiles stacked in Switchgear Room ready for installation

Floor tiles stacked in Switchgear Room ready for installation

Work starts on flooring installation in Switchgear Room

Work starts on flooring installation in Switchgear Room

Suspended ceiling grid being installed in to South Comms Room

Suspended ceiling grid being installed in to South Comms Room

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – Internal works

Hosting Suite 1, with adjacent plant corridor

Hosting Suite 1, with adjacent plant corridor

First coat of paint on Switchgear Room, South Comms Room and Goods In

First coat of paint on Switchgear Room, South Comms Room and Goods In

First fix on lighting in Switchgear Room

First fix on lighting in Switchgear Room

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro fit out update – Internal partition walls

Contractors continuing to install dry walling

Contractors continuing to install dry walling at the south side of the facility

Taping and filling the Goods In area and Switchgear Room

Taping and filling the Goods In area and Switchgear Room

Starting to lay out walling to form rooms at the North side of the facility

Detail of the jumbo stud walling, with steel and plywood reinforcement, and a minimum of 1 hour fire rating throughout the facility

Starting to lay out walling to form rooms at the North side of the facility

Starting to lay out walling to form rooms at the north side of the facility

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro office fit-out time lapse video

As previously promised, here’s a time lapse video of the Centro office fit-out… about 2 months work compressed in to two and a half minutes!

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro datacentre fit-out update – Duct installation and drywalling

Progress has been rapid as there are now nearly 30 contractors on-site, so there are quite a few pictures in this update. Scroll down for the full batch!

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Excavations under way for HV substation base

Excavations under way for dedicated on-site HV substation base

25 tonnes of drywall awaiting installation

25 tonnes of drywall awaiting installation

First sheet of drywall being hung!

First sheet of drywall being hung!

View of Switchgear and South Comms Room taking shape

Switchgear and South Comms Room taking shape (after only 5 hours!)

Internal view of Switchgear Room, very fetching in pink!

Internal view of Switchgear Room, very fetching in pink!

Work starts on the next 120m of duct, this time on public highway

Work starts on the next 120m of duct installation, this time on public highway

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Progress at Centro datacentre

Our contractors have been hard at work on-site at our new Centro datacentre facility over the past week — working 12 hour days, including the weekends!

Progress has been fantastic, with the structural elements of the secure “pod” for the Switchgear Room and South Comms Room completed and the roof starting to go in, and work starting on the steels for our staff room, store and build rooms, North Comms Room and the first part of Hosting Suite 1:

First stage of roofing being fitted to Switchgear Room

First stage of roofing being fitted to Switchgear Room and South Comms Room

First stage of structural work on North Comms room and Hosting Suite 1

First stage of structural work on North Comms room and Hosting Suite 1

We’ve also started work on the ducting that will connect us to our HV power supplies and fibre network connection points:

Cutting the road surface for duct installation

Cutting the first 120m of road surface for duct installation

Laying duct and warning tape within the excavated trench

Laying duct and warning tape within the excavated trench

As we’re installing our own private duct work for the connections, our electricty providers have been on-site to inspect and approve the quality of the works:

Inspection of works by the electricity board

Inspection of works by the electricity board

After only 1 days work, backfilling the trenching was started!

After only 1 day of work, our contractors started backfilling the trenching

We’ve also been installing a comprehensive external digital CCTV and PIR lighting system, with work going on late in to the evening:

Installation of external digital CCTV cameras

Installation of external digital CCTV cameras

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Delivery of steels and roofing for secure “pods” at Centro

Delivery of steels and roofing for secure "pod" mezzanine structure

Delivery of steels and roofing for secure "pod" mezzanine structure

Delivery of steels and roofing for secure "pod" mezzanine structure

Delivery of steels and roofing for secure "pod" mezzanine structure

Work starts on switchgear room, goods in area and south comms room

Work starts on switchgear room, goods in area and south comms room

Progress after 1 days work on switchgear room, goods in area and south comms room

Progress after 1 day with switchgear room, goods in area and south comms room

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Office fit-out underway at new Centro datacenter site

Our contractors are hard at work at our new site getting the office ready for use. New wiring, partitioning, lighting, doors, etc are all going in before Christmas.

Centro office fit-out

Centro office fit-out

Stay tuned as hopefully we’ll have a timelapse video to post once everything’s complete…