Progress has been rapid as there are now nearly 30 contractors on-site, so there are quite a few pictures in this update. Scroll down for the full batch!

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Excavations under way for dedicated on-site HV substation base

25 tonnes of drywall awaiting installation

First sheet of drywall being hung!

Switchgear and South Comms Room taking shape (after only 5 hours!)

Internal view of Switchgear Room, very fetching in pink!

Work starts on the next 120m of duct installation, this time on public highway