Centro update – Raised access floor and suspended ceilings

First 1,000 floor tiles arrive on-site

First 1,000 floor tiles arrive on-site

Floor tiles stacked in Switchgear Room ready for installation

Floor tiles stacked in Switchgear Room ready for installation

Work starts on flooring installation in Switchgear Room

Work starts on flooring installation in Switchgear Room

Suspended ceiling grid being installed in to South Comms Room

Suspended ceiling grid being installed in to South Comms Room

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Internal works

Hosting Suite 1, with adjacent plant corridor

Hosting Suite 1, with adjacent plant corridor

First coat of paint on Switchgear Room, South Comms Room and Goods In

First coat of paint on Switchgear Room, South Comms Room and Goods In

First fix on lighting in Switchgear Room

First fix on lighting in Switchgear Room

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro fit out update – Internal partition walls

Contractors continuing to install dry walling

Contractors continuing to install dry walling at the south side of the facility

Taping and filling the Goods In area and Switchgear Room

Taping and filling the Goods In area and Switchgear Room

Starting to lay out walling to form rooms at the North side of the facility

Detail of the jumbo stud walling, with steel and plywood reinforcement, and a minimum of 1 hour fire rating throughout the facility

Starting to lay out walling to form rooms at the North side of the facility

Starting to lay out walling to form rooms at the north side of the facility

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro office fit-out time lapse video

As previously promised, here’s a time lapse video of the Centro office fit-out… about 2 months work compressed in to two and a half minutes!

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro datacentre fit-out update – Duct installation and drywalling

Progress has been rapid as there are now nearly 30 contractors on-site, so there are quite a few pictures in this update. Scroll down for the full batch!

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Final reinstatement works for first stage of duct installation

Excavations under way for HV substation base

Excavations under way for dedicated on-site HV substation base

25 tonnes of drywall awaiting installation

25 tonnes of drywall awaiting installation

First sheet of drywall being hung!

First sheet of drywall being hung!

View of Switchgear and South Comms Room taking shape

Switchgear and South Comms Room taking shape (after only 5 hours!)

Internal view of Switchgear Room, very fetching in pink!

Internal view of Switchgear Room, very fetching in pink!

Work starts on the next 120m of duct, this time on public highway

Work starts on the next 120m of duct installation, this time on public highway