Centro update – Suite 1

Starting hanging ceiling grid in Suite 1

Starting hanging ceiling grid in Suite 1

Ceiling tiles being installed in to new grid

Ceiling tiles being installed in to new grid

Starting fitting of raised access floor

Starting installation of raised access floor and construction of plant room wall

Starting work in Suite 1 plant room

Starting work in Suite 1 plant room

Flooring work in Suite 1

Flooring work in Suite 1

Ceiling grid showing vented tiles for hot air plenum

Ceiling grid showing vented tiles for hot air return plenum