Merry Christmas!

We’d like to take this opportunity to thank all of our customers for their support and business over the previous 12 months, and wish everyone a very merry Christmas and a happy and prosperous New Year.

Instead of sending out Christmas cards this year we have again made a donation to Great Ormond Street Hospital for Children where over 150,000 sick children are treated every year.

We’d also like to particularly thank our NOC Technicians and Security Officers who are staffing both our LHC and Centro sites on a 24/7 basis over the entire holiday period in order to provide our customers with the continuous support they’re used to!

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro generator snow start test

As part of our extensive Planned Preventative Maintenance (PPM) schedule at our Centro datacentre facility, we run start tests on our generators every two weeks.

These generators provide stand-by power in the unlikely event of a utility outage on both HV supplies to the datacentre. We store enough diesel on-site to run the entire facility for around 4 days, and we have fuel resupply agreements with multiple fuel providers to ensure we can continue operating from generator power even in case of a prolonged outage.

We posted an image of the snow that had settled at Centro over on our Twitter page (over a foot deep in most places!), but as a generator start test was scheduled for today, we’ve uploaded the CCTV footage as an extra bonus:

Our generators are constantly heated and their starter batteries kept fully charged to ensure they are available as quickly as possible to provide backup power to our facility.

During this start test, the outside temperature was around -1C, and both generators started, synced and closed their breakers on to our main switchgear in 18 seconds, well within normal operating tolerances (we have battery supplies for our UPS system to last around 10 minutes before the generators kick in). The generators are run for around 30 minutes, during which time the on-board management computers are checked to ensure that there are no faults.

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Gyron’s Centro facility shortlisted for Datacenter Leaders’ Awards 2009

We’re pleased to announce that our Centro datacentre facility has been shortlisted in the Datacenter Leaders’ Awards 2009 for theĀ  “Innovation in the Medium Datacentre” category. The awards are judged by industry specialists, including engineers from Morgan Stanley, HP, Norland, Dell, and APC, and are sponsored by the British Computer Society, and the Green Grid.

20 rack pod in Suite 1 with hot aisle containment

Hot aisle containment in Suite 1 at Centro datacentre facility

The annual awards are organised by DatacenterDynamics, an information provider who host a series of 22 annual popular datacentre industry conference events worldwide. In 2008 alone, nearly 8,000 industry specialists attended the conferences.

Robin Balen, Managing Director of Gyron stated:

We’re extremely proud to have been shortlisted for this prestigious leadership award. We have received incredible feedback from both existing and new customers who have toured our state-of-the-art Centro facility, which has been designed from the ground up to host a wide range of customer equipment in the most efficient and scalable way possible. This level of recognition from industry insiders is icing on the cake for all the hard work our team have put in to developing the Centro datacentre.

For more details regarding the other awards and finalists, the DatacentreDynamics press release can be found here.

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

UKDedicated Case Study: Anatomy of a datacentre server relocation project

Gyron recently completed a major datacentre relocation project for UKDedicated, a leading provider of managed server hosting solutions. The project spanned 6 months, and concluded with the successful relocation of infrastructure supporting in excess of 200,000 websites to Gyron’s Centro datacentre facility in Hemel Hempstead.

High density colocation racks at Centro following successful relocation

High density colocation racks at Centro following successful relocation

Relocating even a small number of servers between datacentres is a task fraught with potential disaster. When such a project scales up to moving hundreds of servers and dozens of network switches from a live production environment, with strict time frames for acceptable downtime and zero tolerance for hardware failure, the project becomes even more challenging.

Fortunately, in recent years Gyron’s in-house team of engineers have relocated thousands of servers, plus hundreds of storage appliances, network switches, routers, firewalls and KVM units for a wide range of high profile clients.

Craig Robinson, Managing Director of UKDedicated, continues:

When we started the process of exploring new facilities to meet our rapidly expanding datacentre hosting requirements, the viability of the relocation project to move the considerable amount of existing live equipment from our two old locations to the new Centro datacentre was absolutely critical. Gyron were able to offer us everything we needed, from the high specification colocation facility itself, all the way through to the detailed planning and execution of the complex relocation project.

The project was complicated by the fact that during the relocation exercise, equipment was consolidated from two entirely separate datacentres, each with very different procedures and goods handling facilities. Ben Miller, Operations Director of Gyron, stated:

We started the project by thoroughly auditing the equipment hosted at both legacy datacentres, then sat down with UKDedicated and worked through various different relocation strategies. After reviewing UKDedicated’s priorities for the relocation and the types of equipment in use, and comparing this with our previous experience carrying out similar relocation projects, we agreed on a hybrid approach.

The older equipment in both legacy facilities was de-racked, transported to Centro on pallets then re-racked in to new cabinets in their new location. This had the added benefit of allowing UKDedicated to consolidate their older equipment in to fewer racks in order to take advantage of the high density hosting available at the Centro facility.

The newer servers were relocated by mounting the entire rack enclosures with all servers in-place on to a custom designed shock pallet, then crating the rack up and securely transporting it to their new home in the Centro datacentre.

The equipment was fully insured thoughout the relocation project by Gyron, and all hardware was escorted by a datacentre security guard during the move. Downtime was restricted to between midnight and 6AM at weekends only throughout the project in order to minimise the impact on UKDedicated’s clients.

Robin Balen, Managing Director of Gyron, concluded:

Completing this kind of complex datacentre relocation project on-time, on-budget, and with zero hardware failures really demonstrates our strength in providing integrated datacentre services. I’m proud of our team for their hard work over an extended period of time to pull this entire project together for UKDedicated.

Shock pallet with ramp

Testing the shock pallet and ramp during dry run at Centro

Custom designed shock pallet with rack secured in place

Custom designed shock pallet with rack secured in place

Unloading rack crates at straight in to loading dock

Unloading rack crates at Centro, straight in to the loading dock

Unpacking server racks at Centro

Unpacking server racks at their new home in the Centro datacentre facility

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Settle your Gyron invoices by Direct Debit

We’re pleased to announce that Gyron are now able to accept payment via the popular Direct Debit scheme.

Why pay by Direct Debit?

  • It’s quick and easy. Simply fill in the attached form. Within 14 days, the new payment method will be live on your account.
  • It’s convenient. We will automatically take payment for the correct amount just before an invoice is due. You’ll still receive electronic invoices as you do right now.

To set-up Direct Debit payments for your account, please email billing@gyron.net to request a Direct Debit Mandate form.

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]