Time-lapse video showing LHC 2nd floor rack fit-out

We recently fitted out around 2,200 sq ft of new datacenter space at the London Hosting Center.

After the core plant equipment (e.g. air conditioning down-flow units, FM200 fire suppression etc) was installed, the IP CCTV cameras went up and we were able to grab images to make the following time-lapse movie showing all 68 APC NetShelter enclosures being installed over a 4 day period:

Thanks to all of our techs on-site and our fit-out contractors for the hard work getting this new suite online!