Centro update – LV Switchgear and PDUs

Delivery arrives on-site

Delivery arrives on-site

Loading LV switchgear in to the Switchgear Room

Loading LV switchgear in to the Switchgear Room

Positioning first LV switchgear panels

Positioning first LV switchgear panels

Suite 1 LV panel installed and ready for testing

Suite 1 LV panel installed and ready for testing

Dual incoming 2,500A breakers on Suite 1 LV Panel

Dual incoming 2,500A breakers on Suite 1 LV Panel

PDUs installed in to Suite 1 Plant Room

PDUs installed in to Suite 1 Plant Room

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – FM200, power tray work and air conditioning ducting

FM200 gas installation in to Switchgear Room

FM200 gas installation in to Switchgear Room

Heavy duty tray work for LV cabling to Suite 1

Heavy duty tray work for LV cabling to Suite 1

Forming ducting for air conditioning in the comms rooms

Forming ducting for air conditioning in the comms rooms

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Suite 1

Starting hanging ceiling grid in Suite 1

Starting hanging ceiling grid in Suite 1

Ceiling tiles being installed in to new grid

Ceiling tiles being installed in to new grid

Starting fitting of raised access floor

Starting installation of raised access floor and construction of plant room wall

Starting work in Suite 1 plant room

Starting work in Suite 1 plant room

Flooring work in Suite 1

Flooring work in Suite 1

Ceiling grid showing vented tiles for hot air plenum

Ceiling grid showing vented tiles for hot air return plenum

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Biometric man-trap

Bullet proof glass sliding doors awaiting installation

Bullet proof glass sliding doors awaiting installation

Installing door frame in to opening

Installing door frame in to opening

Installing roof on to door

Installing roof on to man-trap

Secure door portal installed and ready for use!

Biometric man-trap installed and ready for use!

Door protected, with reinstatement works underway

Door protected whilst reinstatement works are underway

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – HV switchgear connections

Gyron sign on HV substation enclosure

Gyron sign on HV substation enclosure

Cross section through the HV cabling

Cross section through the HV cabling

Testing redundant HV connections in to the switchgear

Testing redundant HV connections in to the switchgear