Centro update – Final air conditioning works

Finalising lagging for the chilled water pipework

Finalising lagging for the chilled water pipework

Setting flow rates for the chilled water valves

Setting flow rates for the chilled water valves

Commissioning the air conditioning chillers

Commissioning the air conditioning chillers

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – HV transformer installation and chiller pipework connections

3MVA HV transformer installed within secure compound

3MVA HV transformer installed within secure compound

HV feed from our dedicated substation being terminated

HV feed from our dedicated substation being terminated

First of 24 LV cables connecting the transformer and switchgear panels

First of 24 LV cables connecting the transformer and switchgear panels

Final connections being made on chilled water pipework

Final connections being made on chilled water pipework

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – LV power connections

LV cable ready for installation

LV cable ready for installation

Cables ready for 2,500A interconnect to Suite 1 LV panel

Cables ready for 2,500A interconnect to Suite 1 LV panel

2,500A interconnect between switchgear panels installed

2,500A interconnect between switchgear panels installed

LV distribution cables installed on to heavy duty traywork

LV distribution cables installed on to heavy duty traywork

A+B 32A under-floor commando outlets being installed

A+B 32A under-floor commando outlets being installed in Suite 1

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Chillers

Chillers arrive on-site with a Rig Lift

Chillers arrive on-site with a Rig Lift

Offloading first chiller on to the pre-prepared plinths

Offloading first chiller on to the pre-prepared plinths

Preparing to position the second chiller

Preparing to position the second chiller

Both chillers in place and ready for pipework connections

Both chillers in place and ready for pipework connections

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – CRAC units

Computer Room Air Conditioning units (CRACs) arrive on-site

Computer Room Air Conditioning units (CRACs) arrive on-site

Unloading delivery of CRACs

Unloading delivery of CRACs

Interior view of CRAC unit

Interior view of CRAC unit

CRAC bases positioned in the Suite 1 Plant Room

CRAC bases positioned in the Suite 1 Plant Room

First CRAC unit installed on to base

First CRAC unit installed on to base

First three CRAC units installed

First three CRAC units installed