Centro phase 2 fit-out update

Followers of our Twitter feed have been enjoying some behind the scenes photos from the expansion works at our Centro facility. We’ve put together a quick post here with some highlights:

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Gyron celebrates 10th birthday with £3.85m in new contract wins

Gyron, a leading UK  provider of specialist datacentre services, has celebrated it’s 10th birthday in style by announcing a large expansion at its state of the art Centro datacentre following contract wins in excess of £3.85m for services at the facility alone since first opening 9 months ago.

Centro datacentre

Centro datacentre

Robin Balen, Managing Director, comments:

The next phase of expansion at the Centro datacentre is an exciting time for Gyron. Our philosophy has always been that customers will respond enthusiastically when presented with a state of the art datacentre, a flexible approach, fantastic customer service and great value for money, and we’ve been bowled over by the volume of positive feedback about our facility from both new and existing customers. The contract figures speak for themselves, especially given the challenging wider economic conditions.

The fit out works will add an additional 360kW of IT capacity within the datacentre at Hemel Hempstead, over 85% of which has already been contracted for. Work on the expansion space is due to complete on the 1st of June, exactly 1 year after the Centro facility first opened its doors to customer equipment.

Ben Miller, Operations Director, continues:

Our approach from day one when designing the Centro facility was to ensure that the datacentre infrastructure was completely modular. This has allowed us to rapidly expand operations at the site to meet unprecedented demand for our services, and also increase the specification of our services when needed to suit specific customer requirements. This next phase is no exception and we look forward to delivering this additional capacity shortly.

State of the art power and cooling systems have been specified for the expansion area, along with a custom hot-aisle containment system designed in-house, allowing a best-in-class target Power usage Effectiveness (PuE) of between 1.3 and 1.4, whilst simultaneously providing enhanced 2N redundancy on the power infrastructure.

For further details on this and future expansion space at the Centro facility, please contact the Gyron sales team.

-ENDS-

About Gyron

Gyron was formed in March 2000, and offers colocation and a wide range complimentary managed services from two facilities — the London Hosting Centre in the heart of the London Docklands, and the Centro datacentre in Hemel Hempstead. Both datacentres are supported by 24/7 on-site teams of engineers and offer redundant power, cooling, and connectivity, all covered by 100% uptime service level guarantees. For more information, visit http://blog.gyron.net/.

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Mini tour of Centro datacentre

Now that our Centro datacentre has been successfully up and running for nearly 2 months, we’ve finally had chance to take some photos showing the completed facility.

With over 70% of the capacity of our first phase of fit-out already sold to customers, we’re already planning the roll out of additional capacity at the site. For more details and pricing, contact sales@gyron.net!

Datacentre lobby area

Datacentre lobby area. All lighting is motion activated to save energy.

Secure areas with fire panels, separate VESDA systems, and access control

Secure areas with fire panels, separate VESDA systems, and access control

Suite 1 with first two pods live, and plenty of expansion room

Suite 1 with first two pods live, and plenty of expansion room

20 rack pod in Suite 1 with hot aisle containment

2x 20 rack pods in Suite 1 with hot aisle containment

Suite 1 Plant Room

Suite 1 Plant Room showing DFUs, FM200 bottles and distribution boards

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Gyron’s new Centro datacentre facility featured in HotLINX magazine

Our new Centro facility is featured in the latest edition of the London Internet Exchange’s HotLINX magazine. You can click the image below to see the article, or download the entire magazine here!

Centro feature in HotLINX 18

Centro feature in HotLINX 18

Continue reading ‘Gyron’s new Centro datacentre facility featured in HotLINX magazine’

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – Final commissioning works

HV feed from EDF fully tested and energised

HV feed from EDF fully tested and energised

UPS batteries ready for installation and testing

UPS batteries ready for installation and testing

Final UPS connections and testing

Final UPS connections and testing

Access control system installed and tested

Access control system installed and tested

Splicing and testing fibre connections for our DWDM ring

Splicing and testing fibre connections for our DWDM ring

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – Final air conditioning works

Finalising lagging for the chilled water pipework

Finalising lagging for the chilled water pipework

Setting flow rates for the chilled water valves

Setting flow rates for the chilled water valves

Commissioning the air conditioning chillers

Commissioning the air conditioning chillers

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – HV transformer installation and chiller pipework connections

3MVA HV transformer installed within secure compound

3MVA HV transformer installed within secure compound

HV feed from our dedicated substation being terminated

HV feed from our dedicated substation being terminated

First of 24 LV cables connecting the transformer and switchgear panels

First of 24 LV cables connecting the transformer and switchgear panels

Final connections being made on chilled water pipework

Final connections being made on chilled water pipework

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – LV power connections

LV cable ready for installation

LV cable ready for installation

Cables ready for 2,500A interconnect to Suite 1 LV panel

Cables ready for 2,500A interconnect to Suite 1 LV panel

2,500A interconnect between switchgear panels installed

2,500A interconnect between switchgear panels installed

LV distribution cables installed on to heavy duty traywork

LV distribution cables installed on to heavy duty traywork

A+B 32A under-floor commando outlets being installed

A+B 32A under-floor commando outlets being installed in Suite 1

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – Chillers

Chillers arrive on-site with a Rig Lift

Chillers arrive on-site with a Rig Lift

Offloading first chiller on to the pre-prepared plinths

Offloading first chiller on to the pre-prepared plinths

Preparing to position the second chiller

Preparing to position the second chiller

Both chillers in place and ready for pipework connections

Both chillers in place and ready for pipework connections

[Digg] [Facebook] [Google] [StumbleUpon] [Email]

Centro update – CRAC units

Computer Room Air Conditioning units (CRACs) arrive on-site

Computer Room Air Conditioning units (CRACs) arrive on-site

Unloading delivery of CRACs

Unloading delivery of CRACs

Interior view of CRAC unit

Interior view of CRAC unit

CRAC bases positioned in the Suite 1 Plant Room

CRAC bases positioned in the Suite 1 Plant Room

First CRAC unit installed on to base

First CRAC unit installed on to base

First three CRAC units installed

First three CRAC units installed

[Digg] [Facebook] [Google] [StumbleUpon] [Email]