Centro update – LV power connections

LV cable ready for installation

LV cable ready for installation

Cables ready for 2,500A interconnect to Suite 1 LV panel

Cables ready for 2,500A interconnect to Suite 1 LV panel

2,500A interconnect between switchgear panels installed

2,500A interconnect between switchgear panels installed

LV distribution cables installed on to heavy duty traywork

LV distribution cables installed on to heavy duty traywork

A+B 32A under-floor commando outlets being installed

A+B 32A under-floor commando outlets being installed in Suite 1

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Chillers

Chillers arrive on-site with a Rig Lift

Chillers arrive on-site with a Rig Lift

Offloading first chiller on to the pre-prepared plinths

Offloading first chiller on to the pre-prepared plinths

Preparing to position the second chiller

Preparing to position the second chiller

Both chillers in place and ready for pipework connections

Both chillers in place and ready for pipework connections

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – CRAC units

Computer Room Air Conditioning units (CRACs) arrive on-site

Computer Room Air Conditioning units (CRACs) arrive on-site

Unloading delivery of CRACs

Unloading delivery of CRACs

Interior view of CRAC unit

Interior view of CRAC unit

CRAC bases positioned in the Suite 1 Plant Room

CRAC bases positioned in the Suite 1 Plant Room

First CRAC unit installed on to base

First CRAC unit installed on to base

First three CRAC units installed

First three CRAC units installed

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – LV Switchgear and PDUs

Delivery arrives on-site

Delivery arrives on-site

Loading LV switchgear in to the Switchgear Room

Loading LV switchgear in to the Switchgear Room

Positioning first LV switchgear panels

Positioning first LV switchgear panels

Suite 1 LV panel installed and ready for testing

Suite 1 LV panel installed and ready for testing

Dual incoming 2,500A breakers on Suite 1 LV Panel

Dual incoming 2,500A breakers on Suite 1 LV Panel

PDUs installed in to Suite 1 Plant Room

PDUs installed in to Suite 1 Plant Room

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – FM200, power tray work and air conditioning ducting

FM200 gas installation in to Switchgear Room

FM200 gas installation in to Switchgear Room

Heavy duty tray work for LV cabling to Suite 1

Heavy duty tray work for LV cabling to Suite 1

Forming ducting for air conditioning in the comms rooms

Forming ducting for air conditioning in the comms rooms

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]