We’re pleased to announce that today is Gyron’s 9th birthday! It couldn’t come at a more exciting time, particularly with our new Centro datacentre facility opening soon and ushering in a new era for the company. Myself and the other Directors would like to thank all of our dedicated and enthusiastic staff for their hard work getting us to this point, and also our customers’ support and encouragement for making our continued growth possible. We look forward to working together for years to come!

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Raised access floor and suspended ceilings

First 1,000 floor tiles arrive on-site

First 1,000 floor tiles arrive on-site

Floor tiles stacked in Switchgear Room ready for installation

Floor tiles stacked in Switchgear Room ready for installation

Work starts on flooring installation in Switchgear Room

Work starts on flooring installation in Switchgear Room

Suspended ceiling grid being installed in to South Comms Room

Suspended ceiling grid being installed in to South Comms Room

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Pulling HV power and fibre cables

Finishing the final leg of duct installation

Finishing the final leg of duct installation

Preparing to pull the first 200m of HV cable ducting

Preparing to pull the first 200m of HV cable ducting

HV cable following pull through initial leg of ducting

HV cable following pull through initial leg of ducting

Preparing North fibre entry point in to the facility

Preparing North fibre entry point in to the facility

Pulling multi-core armoured fibre cable through dedicated duct

Pulling multi-core armoured fibre cable through dedicated duct

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Internal works

Hosting Suite 1, with adjacent plant corridor

Hosting Suite 1, with adjacent plant corridor

First coat of paint on Switchgear Room, South Comms Room and Goods In

First coat of paint on Switchgear Room, South Comms Room and Goods In

First fix on lighting in Switchgear Room

First fix on lighting in Switchgear Room

[Digg] [Facebook] [StumbleUpon] [Twitter] [Email]

Centro update – Chiller and transformer bases

Cutting chiller support pads in to rear plant yard

Cutting chiller support pads in to rear plant yard

Setting concrete bases for air conditioning chillers

Setting concrete bases for air conditioning chillers

Concrete pads ready for chiller installation

Concrete pads ready for chiller installation

Preparing duct from substation to HV transformer

Preparing duct from substation to HV transformer

HV transformer base formed and trenchwork prepared

HV transformer base formed and trenchwork prepared

HV transformer base ready for installation with link to on-site substation

HV transformer base ready for installation with link to on-site substation